In order to accelerate the development of renewable energy to respond to the chain of the energy crisis and the Russian invasion of Ukraine, the European Commission recently proposed a temporary emergency regulation.
This proposal that plans to continue for one year will cancel the administrative red artificial festival of licenses and development, allowing renewable energy projects to be quickly put into operation. It focuses on "the technology and project type with the largest potential and the least impact on the environment".
According to the proposal, the long -term grid permit for the grid permit for artificial structures (buildings, parking lots, transportation infrastructure, greenhouses) and solar photovoltaic permits in the energy storage system in the co -site site is up to one month.
Under the condition that no certain environmental assessment is required, the concept of "active administrative silence" is cited, and these measures will also exempt such facilities and solar power stations with a capacity of less than 50kW.
As part of the measures, solar, heat pumps and clean energy power stations will be regarded as "overwhelming public interests". When meeting the "appropriate relief measures and perform appropriate monitoring to evaluate its effectiveness", these projects will Benefiting from reduced evaluation and supervision.
EU Energy Specialist Kadri Simson said that "the EU is accelerating the development of renewable energy. It is expected that this year's new production capacity will reach a record of 50GW. In order to effectively solve the problem of high electricity prices, ensure energy independence and achieve climate goals, we need to further accelerate the pace. "
As part of the Re Power EU programs announced in March, the European Union plans to raise its solar target to 740GWDC in 2030. This emergency proposal was announced after that. The EU's solar photovoltaic development volume is expected to reach 40GW at the end of this year. However, the committee said that in order to achieve the 2030 target, the development volume needs to be further increased by 50%to reach 60GW per year.
The European Commission stated that the purpose of this proposal is to accelerate the development of the administrative bottleneck in the short term, and to prevent more European countries from the impact of Russia's natural gas weapons, and it is also conducive to reducing energy prices. These emergency regulations are tentatively implemented for one year.
Frans Timmermans, Executive Vice President of the European Green Agreement, said that "renewable energy has achieved three win -win for Europeans: its production cost is lower, which can make our earth cleaner and not manipulated by Russia. This proposal is Quickly realize green transformation and respond to another step in the energy crisis caused by the Russian and Ukraine War. "
By setting the longest permit period for six months, this proposal can also accelerate the re -power supply of renewable energy power stations and simplify the connection process under the conditions of the additional power of 15%of the original project.